iCIndiaCalculators .org Verified 29 October 2026
Home › Construction & Real Estate › Concrete calculator
Construction & Real Estate

Concrete calculator

Enter the pour dimensions and a nominal mix to get cement bags, sand, aggregate and water — with the dry-volume factor stated, not buried.

Last verified 29 October 2026 Sources 3 No sign-up, no storage Formula and sources shown
Your numbers

No sign-up, no storage. Everything is calculated in your browser — nothing you type is sent anywhere. Change any input and press Calculate again.

Checked, not guessed.3 sources, 4 build tests and a changelog are on this page.
Your result
Enable JavaScript to see your result here. The method, formula and reference table below still explain the answer.
The method

How it is calculated

The formula this page actually runs

Concrete is ordered by wet volume but batched from dry materials. The dry-volume factor bridges the two, and the mix ratio splits that dry volume into cement, sand and aggregate.

Formula Wet volume = L × W × D × (1 + extra) · Dry volume = wet × 1.54 · Cement bags = dry × cement part ÷ sum of parts ÷ 0.0347
01

Measure the pour

Length × width × depth in metres gives the wet volume. Add 3–5% for spillage, an uneven base or a slab that is thicker at one end.

02

Convert wet to dry

Dry materials bulk up: the standard factor is 1.54, so 1 m³ of wet concrete needs 1.54 m³ of dry cement, sand and aggregate combined.

03

Split by the mix ratio

In 1:1.5:3 the parts total 5.5, so cement is 1 ÷ 5.5 of the dry volume. Dividing by 0.0347 converts cement volume to 50 kg bags, and the water is 0.50 × cement weight.

The numbers

Nominal mixes and standard factors

Reference values, not hidden defaults
Nominal mixGradeTypical useCement per m³ (approx.)
1 : 3 : 6M10Mass concrete, levelling course4.4 bags
1 : 2 : 4M15Lightly loaded footings, boundary walls6.4 bags
1 : 1.5 : 3M20RCC slabs, beams and columns in homes8.1 bags
1 : 1 : 2M25Higher-grade RCC, water-retaining work11.1 bags
Dry-volume factor1.54Converts wet volume to dry material volume—
One cement bag50 kg = 0.0347 m³Cement at 1,440 kg/m³—
Water-cement ratio0.45–0.55IS 456 limit for normal exposure—
Nominal mixes are for ordinary work. IS 456 requires a design mix for structural concrete; use these figures for ordering and site checks, not as a substitute for the engineer's mix design.
Before you use it

What most pages get wrong

4 things worth knowing before you use the number
01 · Dry volume

1 m³ of concrete is not 1 m³ of materials

Sand and aggregate bulk up when dry, so 1 m³ of wet concrete needs about 1.54 m³ of dry material. Skipping the factor underprices every order by a third.

02 · Cement content

About 8 bags fill a cubic metre of M20

The 1:1.5:3 mix uses roughly 8.1 bags of 50 kg cement per cubic metre. Stronger mixes use more cement, not more sand.

03 · Water

More water is weaker concrete

The water-cement ratio is capped at 0.50 for M20 in normal exposure under IS 456. Extra water makes placing easier and strength lower — never add water to loosen a mix that has started to set.

04 · Design mix

The table is a site estimate, not a design

Nominal mixes are not permitted for structural work above the grades they cover. For slabs, columns and footings, use the design mix and cube test results from your engineer.

Questions

Frequently asked questions

The queries people actually search
How many cement bags are needed for 1 m³ of M20 concrete?+
About 8.1 bags of 50 kg. The dry volume is 1.54 m³; cement is 1 ÷ 5.5 of that, which is 0.28 m³ or about 404 kg. The calculator shows the exact figure for your pour and mix.
What is the dry-volume factor 1.54?+
Wet concrete contains voids and water; dry sand and aggregate bulk up. The 1.54 factor converts a wet volume to the dry material volume needed. It is standard practice for nominal mixes and is shown in the formula box.
How much sand and aggregate for a 150 mm slab of 5 × 4 m?+
The wet volume is 3 m³, 3.09 m³ with 3% extra. For M20 that is 0.87 m³ cement, 1.30 m³ sand and 2.60 m³ aggregate — about 25 bags of cement and 623 litres of water.
Can I use this calculator for a design mix?+
No. A design mix is calculated from required strength, exposure and the actual materials, and comes with trial mixes. Use this calculator for nominal mixes and site ordering only.
Why is the water shown in litres?+
Water is measured by weight in mix design but is dosed by volume on site, and 1 litre of water is 1 kg. The result uses the water-cement ratio you enter, capped at 0.65 here.
How much extra should I order for a slab?+
3% is enough for a flat, well-prepared base. Use 5% for hand mixing, uneven ground or a pour where the formwork may leak. Never order less than the calculated volume.
Trust layer — how to check this page

Sources, dates and a changelog.

Every number this calculator uses is either an input you control or a value from the sources below. The formula is compiled and tested at build time, so the page cannot ship with a broken calculation.

Sources

This page

  • Last verified: 29 October 2026
  • Next review: 29 April 2027
  • Vertical: Construction & Real Estate
  • Build tests: 4 passed
  • Changelog: 1 entry

How we handle errors

  • Spotted a mistake? Report it — we correct and log it.
  • Corrections appear in the changelog below.
  • Read the methodology and the disclaimer.
Changelog
2026-10-29First published.